It’s been a few months since our last update on this project, but the work goes on apace. While the sidewalk work on 40th west of Wallingford Ave. is now more done than not, the No Parking signs have gone up on 40th east of Wallingford Ave., and SDOT is warning of a few weeks of work to take place at the Wallingford/40th intersection. Be aware that the bus stop in front of the Durn Good Grocery Store has been moved about 60 feet east to accommodate this work. Sidewalk work is wrapping up along 50th, but a new work zone will be opened up along Greek Lake Way between 51st and Kenwood Place.
Here are the particulars from SDOT’s latest newsletter:
N 40th St:
- At Stone Way N: expect pedestrian detours, shifted travel lanes, and traffic occasionally reduced to a single lane with flaggers present to rotate traffic
- At Bagley Ave N: expect pedestrian detours and shifted travel lanes
- Wallingford Ave N: We expect to continue work at this intersection for as long as 3 weeks. Expect shifted travel lanes and pedestrian detours.
Green Lake Loop:
- The intersection of West Green Lake Way N and East Green Lake Way N: expect noise, pedestrian detours, and the island to be removed to maintain two-way traffic while we work
You can follow the project updates here.